Emergency powers still an Aquino option

3

President Benigno Aquino has not given up on seeking emergency powers from Congress to address the energy crisis, Malacañang said on Sunday.

Advertisements

But Presidential Communications Secretary Herminio Coloma Jr. made it clear that such powers are not connected with initiatives to open the Constitution to political amendments that would pave the way for allowing the President to run for a second term.

“For the malicious, this has nothing to do with the Charter change some quarters are pushing,” Coloma said in a radio interview.

He added that they were aware of the urgency of resolving the energy crisis and had looked into the options suggested by Energy Secretary Jericho Petilla.

Petilla “already said the President is looking for options, where industry players can help in,” Coloma said.

“We assure the public that the government is doing everything to make sure there is a sufficient supply of electricity,” he added.

Last week, Petilla reported that business establishments were lukewarm to his Interruptible Load Program, where large power users will be paid if they agree to go off the grid and use their generator sets during peak load hours.

He said he was only able to get a commitment of 27 megawatts (MW) from the private sector although Manila Electric Co. or Meralco reported last May that mall owners have committed a total of 110 megawatts to the program.

But Palace spokesman Edwin Lacierda was non-committal when reminded that Aquino only has until the end of the month to decide whether to implement emergency measures to address the power crisis that was predicted by experts as early as last year.

“It is still among the measures being eyed by the President among other possible suggestions given the circumstances, but as to the final decision of the President, let’s just wait for him to issue a directive,” Lacierda said.

The idea to grant emergency powers to the President was suggested by at least nine local and foreign chambers of commerce and even labor groups joined the call because of effects of a power crisis on job generation.

Labor groups also raised the power situation during their pre-Labor Day dialogue with Aquino in April and the President promised that there “will be good news in a couple of days” but there has been no word since.

Last June 18, Petilla convened a task force under the Department of Energy comprised of several stakeholders but the labor groups did not want join the task force because of the supposed lack of coordination among stakeholders.

In July, Petilla, who had repeatedly dodged suggestions to declare a state of emergency in the power sector, finally admitted that Luzon will likely face a power shortfall of between 400 megawatts and 500 MW by summer next year.

He said at least six power plants, capable of producing 400 MW, will likely be online by summer, but that will not be sufficient because other plants are also expected to go off-line for maintenance.

Petilla agreed with the call of the private sector that it was time for Aquino to declare a state of emergency in the power industry so that he can seek remedies.

The President, however, has not acted on the proposal.

But Lacierda noted that Aquino mentioned the matter in his State of the Nation Address and he instructed Petilla to discuss the matter with the Energy Regulatory Commission, the congressional oversight committee and other stakeholders.

“One thing that we want to emphasize is that we are going to pro-actively handle the situation. That’s why we’re recognizing all the concerns of the power sector, as well as the stakeholders, including the citizens,” he said.

Opposition lawmakers, however, suspect that the administration is concocting a power crisis in 2015 to justify emergency powers for the President.

Representatives Neri Colmenares and Carlos Zarate of Bayan Muna said as of 2013, the installed capacity for the Luzon is 12,790 MW with dependable capacity of 11,469 MW, based on Department on Energy figures.

“The peak demand for the grid is just at 8,700 MW plus [this happens on summer, May in particular]and the portion of Meralco in that is at 6,121 MW (based on 2014 figures),” the two said in a statement also on Sunday.

Deducting dependable capacity from peak demand, there should have been allowance for reserves amounting to 2,700 MW, which is more than the 400 MW deficit that Petilla claims, Colmenares said.

House Committee on Energy chairman Reynaldo Umali agreed with the assessment.

“That’s what I’ve been saying ever since the issue broke out,” Umali, who is from the Liberal Party and is Oriental Mindoro’s Second District representative, said in a text message.

Zarate dismissed the power crisis as “nothing but a bogey” to justify emergency powers.

There is enough capacity to cover the supposed shortfall in the energy supply for summer of 2015, he said.

Colmenares said even if there is a power shortfall, the government can tap state-owned power plants like the Malaya power plant and the Sucat power plant.

“This emergency power is even probably designed so that Malacanang can dip its fingers again on the Malampaya fund, the spending of which was already restricted by the November 2013 decision of the Supreme Court,” Zarate said.

WITH A REPORT FROM REINA TOLENTINO

Share.
loading...
Loading...

Please follow our commenting guidelines.

3 Comments

  1. Petilla’s recommendation to give additional power to BS Pnoy is getting crystal clearer every day, one article I’ve read aside from this one that once BS Pnoy will have additional power for Energy Crisis, he can use the Malampaya fund since the fund can use for Energy purposes as per SC decision. So there you go, it all about LP’s campaign fund again for 2016 election. These bunches of viruses and leeches are plaguing our country.

  2. the quick fix will eventually increase the cost of electricity as what happened during the ramos administration to fix the mess that cory’s administration did to the power industry. the only viable option out of this emergency power to augment the power shortage is to get quick dispatch power plants, like rental power and modular fuel oil (diesel & bunker fired) power plants installed. rental power can be dispatched and installed ready to provide electricity in 3~4 months while the fixed fuel oil fired power plants can be constructed ready for commercial operation in less than 1 year. the drawback on these quick dispatch power plats is the high cost of producing power compared to conventional power plants, like coal fired, hydro power and geothermal power plants due to the cost of fuel oil. generation cost will be in the tune of P12~P15/KWh (base cost), excluding transmission & distribution cost, VAT and other miscellaneous cost added to the electric bill of the consumer.

    the irony of this call for emergency power is that those who have money, resources and connections will benefit the most as they can corner the contracts in connivance with those in power in exchange of bribes.

  3. First, BS Aquino has enough power in his hands as it is. Second, emergency power will not add even a single megawatt of electricity to our inadequate supply; only long-term planning and the building additional hydro-electric dams and power generation plants will. Except, it takes 5 to 6 years before the construction of a hydro-electric dam or a power plant will be completed. Aquino should have embarked on the building of more power generation plants 4 years ago.

    For his administration’s lack of foresight and incompetence, he now wants emergency power on the lame excuse that he can’t resolve the looming power crisis without it. No, he won’t.

    Just say NO to giving the incompetent Aquino emergency powers. If we do, this may be the prelude to BS Aquino’s declaring Martial Law next.