The Manila Times

Regions

  Home  

  About Us  

  Contact Us 

  Subscribe     Advertise  
  Archives     Feedback  

  Register  

  Help  

  Top Stories

  Metro

  Business

  Regions

  Opinion

  World

  Life & Times

  Sports

  Tech Times

 
 
 

Wednesday, May 07, 2008

 

SC finds Hanjin liable for construction delay

High Court orders Korean firm to pay a subcontractor in Davao International Airport project

By William B. Depasupil, Reporter

THE Supreme Court (SC) has ordered controversial Korean firm Hanjin Heavy Industries and Construction Co., Ltd. (Hanjin) liable for the delay in the construction of the Davao International Airport project.

As such, the SC’s Second Division ordered Hanjin to pay Dynamic Planners and Construction Corp. (Dynamic), the subcontractor of the project, to pay a total of P352.162 million plus interest.

The amount represents P293.952,273.36 for the final award and P58,210,336 for retention. The SC also ordered Hanjin to pay a separate P500,000 for attorney’s fee.

The 33-page decision penned by Justice Presbitero Velasco, Jr. affirmed with modification an earlier decision by the Court of Appeals (CA) and the Construction Industry Arbitration Commission (CIAC).

The CA had earlier ordered Hanjin a 12-percent interest per annum on the P293.952 million on the net award from the promulagation of the assailed final award on September 7, 2004, until paid. The High Court reduced the interest to 6 percent.

Records show that on August 23, 1999, the Department of Transportation of Communications awarded to Hanjin the construction of the Davao airport for P1.7 billion, 65 percent of which in peso and 35 percent in US dollars.

On Feburary 26, 2000, Hanjin and Dynamic executed a subcontract agreement over a 76.5-percent portion of the main contracts for the price of P924.67 million.

Among others, the subcontract contained provision on advance payment and progress billing, the first item payable within 20 days from the contract signing.

Progress billing represents claims for payment for works accomplished and materials delivered as construction progresses.

On April 2002, when 89 percent of the project had been finished, Hanjin informed Dynamic that no progress billing would be forthcoming after April 2002. As of that time, a total of 20 progress billings were submitted to Hanjin in the total amount of P582.1 million, 10 percent of which, or over P58.2 million, was retained by Hanjin.

Hanjin claimed that Dynamic was delayed in, and eventually abandoned the project, prompting the company to complete what was left behind by Dynamic.

Hanjin thus claims that Dynamic should not be entitled to the retention money and should instead be held liable for damages.

But the Court sustained the CA and CIAC’s findings that Dynamic did not abandon the project.

In its resolution dated August 31, 2005, the CA upheld CIAC’s finding on non-abandonment.

“The CIAC found that Dynamic did not abandon the subcontract works, but that it was squeezed out of the subcontract and was rendered by Hanjin incapable of performing the obligations therein,” the resolution said.

   

Phgifts

philflora.gif

Manila Times Friends

Sponsored Links
 

Back To Top

 
 
 

Severino O. Frayna Jr., Benjie Dela Rosa
Powered by: 
The Manila Times Web Admin.

  

Home | About Us | Contact | Subscribe | Advertise | Feedback | Archives | Help

Copyright (c) 2001 The Manila Times | Terms of Service
The Manila Times Publishing Corp. All rights reserved.

Hosted by: