|
By Moneth G. Deposa, Researcher
First of two parts
Residents of northern Manila are optimistic that
the perennial flooding in their communities will soon end now that
the government has conceived a project that would ease their
sufferings.
For them the ambitious but long-delayed
flood-control project in Caloocan, Malabon, Navotas, Valenzuela (CAMANAVA)
is the much-awaited reality of their dreams—living safe from
floods.
But it seems they are destined to wait again,
now that Public Works Secretary Bayani Fernando confirmed to The
Times that the project is “temporarily on hold” owing to some
“technicalities,” which he declined to elaborate. The future
implementation of the project raised fear and confusion among
residents in northern Manila—fear that the project might fall
through and confusion about what really delayed it.
Camanava concentration
The project, which would improve the
flood-control and drainage system in the region, covers 18.48 square
kilometers of flood-prone areas in the cities of Caloocan, Malabon
and the town Navotas (first phase). A feasibility study on
Valenzuela, Obando and Meycauayan would be made under a separate
drainage plan (second phase).
The camanava project centers on the northern and
southern parts of the Malabon River. Experts propose to build an
8.6-kilometer polder dike—a dam big enough to hold a body of
water—and raise the river wall by 4.4 kilometers as well as sites
for navigation, floodgates and pumping station in the northern area
of the Malabon River.
In the southern part, they plan to raise the
left bank river wall by 1.1 kilometers, the Navotas and Marala river
walls by 1.3 kilometers, construct 4 sites for pumping station with
floodgates, improve drainage channels by 6 kilometers and build a
new drainage channel about 2.7 kilometers. (See tables below.)
The first phase, costing an estimated P5.020
billion to be funded by the Japan Bank for International Cooperation
(JBIC), was supposed to begin construction on March 12 this year and
is scheduled to be completed by March 2007. Experts believe that
this project will mitigate flooding in areas through flood-control
and drainage improvement works, thereby improving the living
conditions of the residents and promoting economic activities in the
areas covered by the plan.
What’s the score?
A source disclosed that this flagship project
has been on hold until the contract is finally signed by Secretary
Fernando as a party to it. The contract has been at his office since
March 7. The JBIC has been following up the contract and other
documents on the project, but to no avail at this writing. Asked
what was delaying the signing by Fernando, the source said the
secretary is considering some modifications on the design, which
seems to accommodate the request of Navotas Mayor Tobias Tiangco.
In a letter to Fernando on March 25, Tiangco
asked the Department of Public Works and Highways to include coastal
dikes in the first phase of the design, which according to
consultants, is difficult to grant because the project is final and
has already been bid out by the winning contractor in accordance
with its original cost and design. All components—big or
small—are subject to contract revision.
The source also said that on March 26, Fernando
called a closed-door meeting with Hitoshi Kin, project manager of
the consultant firm CTI Engineering Co. Ltd., and some engineers of
the project. At first, Fernando asked why the Navotas coastal dike
was not included in the first phase. The engineers defended their
decision, citing factors such as a limited budget and the squatters
in the area. They said the coastal dike was not included in the
second phase because the site is the highest area in Navotas and
won’t easily flood unless there is an extreme high-tide level of
11.93 meters, which seldom occurs, not after 10 years by which time
the engineers are ready with the second phase. On the possibility
that the second phase may fall through, the engineers said the JBIC
assured them that it would fund the second phase, but that the first
phase should begin.
Fernando even suggested that the engineers trim
some of the project components’ cost to include the Navotas
coastal dike, which, according to sources, the engineers ignored.
They said it could not be done, because the project had been bid out
to the winning contractor. Fernando reportedly considered canceling
the project “if the Navotas coastal dike will not be included in
first phase.”
Design ‘flaws’?
In a newspaper story on March 7 the marine
geologist Kelvin Rodolfo noted that the project’s design was
“grossly inadequate” and “dangerous.” He said the estimate
of land subsidence (sinking of land) was based on a 1990 document
that presumed that the use of ground water would end in 1990 and
that the consultants expected the additional subsidence to occur at
a rate of only about one-half centimeter a year, causing only 15
centimeters of land subsidence by the year 2030.
Kin responded that the consultants recognized
that excessive pumping of ground water in Metro Manila had caused
the land to sink and, as a consequence, the sea level to rise.
Kin cited a study on land subsidence by Emmanuel
G. Ramos of the Philippine Institute of Volcanology and Seismology,
which noted that the piezometric map of Metro Manila for 1981-82
showed that the piezometric level had reached -120 meters at Navotas
and Caloocan along with the Pasig-Pateros area, -40 meters for Parañaque
and coastal Pasay City areas and -20 meters for Quezon City,
Muntinlupa and Cavite. (A piezometer measures high pressure.)
|
 |
|
|
Kin said a study by JICA in 1991 showed that the
elevation of the Navotas-Caloocan area remained close to -110
meters; Pasig-Potrero levels recovered to around -30 meters; and
Bacoor-Muntinlupa reached -80 cm. He also cited the unpublished
record of ground-water levels available from the mwss for 1995
showing that the deep piezometer levels in Navotas-Caloocan appear
to have retained its -100-meter level, and that the deep levels in
Quezon City and Marikina appear to have recovered. Bacoor, Las Piñas
and Muntinlupa appear to have reached a deeper -100-meter level,
although the depressed area seems to have shrunk.
Kin noted that as regards the excessive
withdrawal or decline of ground water, Valenzuela and Malabon, where
the polder dike is located, are not mentioned. “Considering the
aboveground water conditions, the consultants drew up some
countermeasures to address land-subsidence concerns in the
structural design especially those of pumping station and
flood-control gates.”
For the polder dike, which technically may be
raised in accordance with the progress of actual subsidence, an
extra embankment of 0.30 meter with slope protection is considered a
countermeasure for the initial settlement of the foundation,
providing for regular maintenance work according to the actual
settlement in the future.
Rodolfo said the consultants “totally
ignored” in the design the effects of powerful winds, surge and
waves that come with storms in Manila Bay, an assertion that Kin
disputed. He said Rodolfo was referring to the dike in the coastal
areas of Navotas, which are not exposed directly to storm surges in
Manila Bay.
In the design of the Navotas navigation gate
structure, however, Kin said the force of the wave approaching the
gate was computed and considered in the structural analysis.
Rodolfo alleged that the project designers
ignored their own analyses that indicate the need to base their
polder dikes with piles driven deeply through at least 15 meters of
soft bay sediment. Kin said that in building the polder dike, which
was 8.5-km long, the designers did not consider the use of pile
foundations practical, because of the prohibitive cost. Therefore,
the designers adopted alternative countermeasures such as bamboo
rafts with geosynthetics and sand mat foundation. The additional
height of the embankment, Kin said, was also considered in the
initial settlement of foundation as well as the regular maintenance
work in accordance with the progress of the land settlement.
In his 1995 book Pinatubo and the Politics of
Lahar, Rodolfo, also a consultant of the National Institute of
Geological Sciences (NIGS) at UP Diliman, cited documents and
historical facts as the bases for his allegations. He said his group
warned the Department of Public Works and Highways publicly and
privately against containing lahar with flood-control technology
because the volcanic deposit is so much more powerful than water
floods, and it behaves differently. Since then, Rodolfo’s group
had warned people in harm’s way about inadequate dikes that indeed
eventually failed, citing experiences in Pinatubo (1991), the
Pasig-Potrero lahar-dike (1995) and the FVR megadike system (1996).
To the assertion that he is not a designer who
would know the factors to consider in a design, Rodolfo replied that
geologists are the ones who gather fundamental scientific data used
by structural designers elsewhere in the world to build proper
containment structures. Geologists, he said, are more knowledgeable
about the energies and behaviors of storm waves and surges.
Where does it begin?
In early February Rodolfo conducted a seminar on
land subsidence but consultants and designers of the CAMANAVA
flood-control project could not attend and instead sent somebody to
represent them.
On Feb. 12 the group asked Rodolfo to have an
informal discussion with them about the seminar. The meeting took
place at the NIGS office in Diliman. According to a source, the
dialogue dealt with land subsidence and other information about it,
but not the design or the land subsidence used in the CAMANAVA
project. Rodolfo even asked for a final copy of the main design of
CAMANAVA for future reference.
On March 7 Rodolfo noted in a newspaper story
that the design of the CAMANAVA project was “grossly inadequate”
and “dangerous.” He alleged that the consultants used
obsolete and erroneous data in determining the height of the 8-km
polder dike, based on the old subsidence rates, or how fast the four
cities are sinking into the water. Within a few days, the
consultants of the project disputed Rodolfo’s allegations.
A source told The Times that weeks after the
consultants responded to Rodolfo’s allegation of flaws in the
design, both camps had made no effort to meet again or talk about
the issue. This led the designers to conclude that the issues, which
have been raised in the media, are “just allegations” without
bases. Even the Public Works secretary, Bayani Fernando, once quoted
as saying “technical opinions and warnings do not always come
true,” implicitly doubted Rodolfo’s judgment on the project
design.
The consultants are confident that the design
they made is certain that it passed several assessing bodies like
Bureau of Design, NEDA Board with President Arroyo as the approving
chairman, and counterpart bodies from the funding institution,
Japan Bank for International Cooperation.
Conclusion
|