Wind turbines for testing

0

PetroWind Energy Inc. (PWEI) will start commissioning tests for the first eight of its wind turbine generators (WTGs) at its wind power project in Nabas, Aklan in January next year. The commissioning tests will be for a period of two months from January 17 to March 17, 2015. The Energy Regulatory Commission (ERC) approved PWEI’s application to develop, own, and operate dedicated point-to-point facilities connecting the Nabas wind farm to the National Grid Corporation of the Philippines’ (NGCP) Nabas-Caticlan 69Kv overhead transmission line.